2009-2011 Rehabilitation of Arzni Shamiram, Low Hrazdan, Artashat and Shirak Main Canals

The Client: “Millennium Challenge Foundation” SNPO

The canals were rehabilitated within  their own frames.

The following was implemented for rehabilitation:
– Clean the canals from sediments and vegetation;
– Demolition of concrete offsets;
– Clean the canal bottom and walls of deteriorated concrete;
– Fill in the cavities with B7.5 class concrete
– Cover the bottom of the canal with B 12.5 concrete
– Cover the existing concrete with 10cm of B 12.5 concrete on the trapezoidal parts of the canal, etc.
– Plan transverse joints of 4m from each other all along the canal
– Repair water dischargers by installing new valves
– Dismantle the existing slabs and install new ones, replace reinforced concrete slabs in the places where the walls are covered where (3×1.5)m reinforced slabs
– Create a preparatory layer of B 7.5concrete behind the slabs.

The following scope of work was implemented:

1. Clean the canal of sediments  21300 m3
2. Earthworks 11400 m3
3. Pebble graveling underneath the concrete cover 2400 m3
4. Gabion masonry 600 m3
5. Dismantle of old concrete and reinforced concrete 14200 m3
6. Clean concrete surface 123500 m2
7. Monolithic reinforced concrete installation 16600 m3
8. Reinforcement 192 t
9. Shotcrete 41500 m2
10. Construction of joints 37100 m