Argel HPP. The chute of no-operation spillway.
1997-1999 Argel HPP. Repair-rehabilitation Works. The Chute of No-operation Spillway

The Client: SE “Sevan-Hrazdan Cascade of HPP” CJSCo. RA

The rehabilitation of the chute was stipulated by the need to secure normal and stable operation of one of the largest HPP on the Hrazdan River after the destruction of the active chute as a result of a landslide down the hill, on the slope of which it was situated. The works on the new route were conducted on the mountainside with a slope from 28° to 32°. The works on the route in mountainous terrain required the application of special engineering solutions and technological schemes.

As a result the following rehabilitation works have been implemented on 343.1 m long reconstructed section and newly projected 635 m long stretch:

 

1. Earthworks  212 876.9 m3
2. Drilling-and-blasting works  34600 m3
3. Concrete and reinforced concrete  11596.0 m3
4. Installation of reinforcement  433.6 t
5. Steel structures  50.6 t
6. Joints (metallic keys)  1321.7 m
7. Ф 530 mm built-in-place reinforced concrete piles  405 m
8. Consolidation grouting  491.4 m
9. Masonry work  34.8 m
      10. Laying of low-voltage and high-voltage cables  2694 m
      11. Laying of pipelines  1969m
      12. Preparation of peddle gravel mattress  2879.7 m3
      13. Insulation works  5057.0 m2
      14. Asphalt carpet  3905 m2
      15. Precast reinforced concrete (reinforcement of covering) 99.6 m3
      16. Painting of steel structures  640 m2
      17. Drilling of wells  690 m