2011 Reconstruction of Flush Weir of the Intake Unit of Noyemberyan 1-st Stage Pumping

The Contractor: the Armenian Branch of “FARMEX Technologies” Ltd.

The following scope of work was implemented:

1. Earthworks  91768 m3
2. Concrete and reinforced concrete  4062 m3
3. Expansion and movement joints 1000m
4. Drainage pipline  860m